Case
Studies of Timber Construction Structures
Timber
Construction at Meadow Point, Phase II
Project Summary
Project
located in large Master Planned residential development
community with strict environmental standards. Permitting
for the project exceeded 7 months after meeting requirements
from three regulatory agencies. Challenges for this project
were economic constraints, 6’ wide timber boardwalk design
to be built from the top that met ADA compliance for
handrail. All challenges were satisfactorily met with over
2000 linear foot constructed.
Project Staff
Project Details
-
Project
Details
-
County
Line Road separating Hillsborough and Pasco Counties
in Florida Completed May 2006
-
Shows
capacity to build a top build 6’ wide structure
-
2,080
ft. of nature trails
-
Four
pre-bid contractors, SunBelt was the only bidder
with capabilities
-
Interesting Additional Info
-
Pre /
During / Post (recent project newest pictures)
-
Arial
of the project (get from developer)
|